COMMON CONVERSIONS | |
1 Acre
1 Acre Inch 1 Acre Inch/Hr. 1 Acre Foot 1 Bar 1 Cubic Foot 1 Cubic Foot 1 Cubic Foot/Sec. 1 Cubic Foot/Sec. 1 Foot 1 Gallon 1 Gallon 1 Gallon 1 Gallon/Min. 1 Gallon/Min. 1 Horsepower 1 Horsepower 1 Horsepower 1 Kilowatt 1 Kilowatt 1 Kilowatt Hr. 1 Liter 1 Pound 1 PSI 1 PSI 1 Square Mile 1 Ton |
43,560 Square Feet
27,154 Gallons 452.57 Gallons/Min. 325,851 Gallons 14.50 PSI 7.481 Gallons 62.3554 Pounds 0.646317 Million Gallons/Day 448.831 Gallons/Min. 0.433 PSI 0.1337 Cubic Feet 3.785 Liters 8.3453 Pounds 0.002228 Cubic Feet/Sec. 8.02083333 Cubic Feet/Hr. 550 Foot Pounds/Sec. 0.746 Kilowatts 746 Watts 56.92 BTU/Min. 1.341 Horsepower 3,413 BTU 0.2642 Gallon 0.1198 Gallon 0.0689 Bars 2.31 Feet 640 Acres 2,000 Pounds |
BASELINE NOZZLE GPM ON TYPICAL 23˚ BRASS IMPACT SPRINKLER |
||||
PSI | 3/32 | 7/64 | 1/8 | 9/64 |
25 | 1.28 | 1.72 | 2.20 | 2.83 |
30 | 1.41 | 1.89 | 2.41 | 3.11 |
35 | 1.52 | 2.04 | 2.61 | 3.36 |
40 | 1.63 | 2.18 | 2.79 | 3.60 |
45 | 1.73 | 2.31 | 2.96 | 3.82 |
50 | 1.83 | 2.44 | 3.13 | 4.03 |
55 | 1.92 | 2.56 | 3.28 | 4.23 |
60 | 2.01 | 2.67 | 3.43 | 4.43 |
65 | 2.09 | 2.78 | 3.57 | 4.61 |
70 | 2.18 | 2.89 | 3.71 | 4.79 |
Courtesy Weather Tec Corporation |
TORO DRIP TIPS
Courtesy of Toro Ag
COMMON DRIP TAPE DAMAGE
Courtesy of Toro Ag
INJECTOR SELECTOR
Courtesy of Mazzei
IN DEPTH AG
Courtesy of RCD Santa Cruz
- Sizing mainline from flowrate
- Leaching requirement guide
- Estimate N in water
- Estimate the application rate
FORMULAS
Precipitation Rate (inches/hour)
= 96.25 x Total GPM
Total Area (sq ft)
Application Rate
R = Q x T = 450GPM x Time
A Acres
R = inches
Q = flow rate (acre inches per hour) = 450GPM
T = running time
A = area covered in acres
Number of Rolls of Drip Tape Needed Per Field
522720″ ÷ Bed Center (in.) x Total Acres ÷ Roll Length (in.) = Total Rolls
Drip Tape GPM Per Acre
522720″ ÷ Bed Center (in.) ÷ 100 x Tape Flow Rate per 100′ (e.g.: 0.67) = GPM per Acre